Con-Tec Solutions
Platt Bridge Health Centre Transforming Healthcare Lighting Through Smart Technology
HealthcareEric Wright Group

Platt Bridge Health Centre Transforming Healthcare Lighting Through Smart Technology

£400K
Contract value

£400K

A comprehensive lighting modernisation at Platt Bridge Health Centre, introducing intelligent LED technology and advanced emergency lighting to enhance energy efficiency, reliability and long-term performance.

Floors served

3

A total of fluorescent light fittings replaced to LED across all three floors, including high level atrium feature lighting.

Unplanned Outages

0

Zero unplanned supply interruptions across the full programme on a live acute site with 24-hour clinical operations.

The Brief

The project involved a comprehensive upgrade of the lighting infrastructure at Platt Bridge Health Centre, incorporating intelligent LED luminaires with daylight-responsive dimming and presence detection to improve energy efficiency and reduce operating costs. A key element was the high-level atrium lighting installation, requiring specialist access equipment and precise adherence to the lighting design specification to achieve optimal illumination levels. The upgrade also included an intelligent, addressable wireless emergency lighting system, providing automated testing, enhanced monitoring and improved long-term maintenance efficiency.

Platt Bridge Health Centre LED lighting upgrade Atrium Lights

High level Atrium Lighting

High level atrium lighting installation using specialist access equipment, delivered to a lighting design specification to achieve the correct levels.

Atrium Lighting High Level Platt Bridge
“A clean, well-coordinated package from subcontractor through to final test — exactly what a £400k electrical scope on a fast-track commercial programme needs.”

— Eric Wright Group Site Manager

Distribution board installation during commercial fit-out
Emergency lighting commissioning on a commercial development

Delivered on Programme

Final energisation was achieved on the agreed date, enabling the developer's practical completion milestone. Full O&M documentation, test certificates and as-installed drawings were submitted within two weeks of completion.